College Hills Boulevard project update - paving schedule
When: Dec. 12
Where: College Hills Boulevard from Millbrook Drive to W. Loop 306 Frontage Road
- First layer of paving will cover west side of road and connect to side streets.
- Final layer of paving for entire roadway from Millbrook Drive to W. Loop 306 Frontage Road will take six days. All signals will then become active. Striping will come later, but two-way traffic will be allowed across the full road until then.